Sunday 18 May 2014

WEEK 9

Date : 7 April 2014

Title : Flow Chart & Gannt Chart Of the Project

Objective :

  • To identify the flow of project operations.
  • to follow the guideline date that we have made.

Content / Producer : Figure below were our Flow Chart & Gannt Chart for our the Project

Result:
  1. Figure below show our Flow Chart:

Gantt Chart:


BIL
TASK NAME
DURATION
START
FINISH


1
Start
0 days
Mon-3-Feb-14
Mon-3-Feb-14
2
Find the supervisor
8 days
Mon-10-Feb-14
Mon -17-Feb-14
3
Find the tittle
10 days
Tue-18-Feb-14
Thu-27-Feb-14
4
Discuss the project
15 days
Fri-28-Feb-14
Fri-14-March-14
5
Research from internet
18 days
Mon-17-March-14
Thu-3-April-14
6
Research from advisor
15 days
Fri-4-April-14
Fri-18-April-14
7
Research from book
18 days
Mon-21-April-14
Thu-8-May-14
8
Find the best components
20 days
Fri-9-May-14
Wed-28-May-14
9
Find the best place to find the components
20 days
Thu-29-May-14
Thu-17-June-14
10
Buying the components
30 days
Wed-18-June-14
Tue-17-July-14
11
Component test
18 days
Fri-18-July-14
Mon-4-Aug-14
12
Planning the project step by step
16 days
Tue-5-Aug-14
Wed-20-Aug-14
13
assemble all the component
18 days
Thu-21-Aug-14
Mon-8-Sep-14
14
Construct the circuit
18 days
Tue-9-Sep-14
Fri-26-Sep-14
15
Install circuit in component
18 days
Mon29-Sep-14
Tue-16-Oct-14
16
Testing the device
11 days
Fri-17-Oct-14
M0n-27-Oct-14
17
Analysis
10 days
Tue-28-Oct-14
Thu-6-Nov-14
18
Project complete
15 days
Mon-10-Nov-14
Mon-24-Nov-14
19
Preparation power point presentation
7 days
Wed-26-Nov-14
Wed-3-Dec-14
20
Presentation the project
1 day
Mon-8-Dec-14
Tue-9-Dec-14
21
Finish
1 day
Mon-15-Dec-14
Tue-16-Dec-14Result: We understood on how to take care of this device. 






























   

Conclusion: After produce the Flow Chart , our operation of project become easier. While the Gantt chart will guide us complete the project according to our time planning.

No comments:

Post a Comment